Running cost of fiber laser cutting machine+Karina

How to Running cost of fiber laser cutting machine

How to Running cost of fiber laser cutting machine, fiber laser cutting machine running cost total include 3 partselectric powerauxiliary gas and quick wear parts.
Then, compared with other cutting equipment, fiber laser cutter should be the lowest.

Firstly. Running cost of fiber laser cutting machine-Electric power
1500w Raycus XTC-F1530WT  rated power is 24KW.

Real machine running cost occupy 60%~70% of whole power, so the real electric power cost is 14~17kw/h.

Secondly. Running cost of fiber laser cutting machine-Auxiliary gas consumption
One gas tank is 40L in China.
A. N2 gas consumption is same for different thickness SS. Its consumption of continue cutting is about 20~30min/tank.
B. O2 gas consumption is decline when CS thickness increase. The thicker CS, the less gas consumption.
For example,
1mm CS cutting gas consumption is about 50~60min/tank.
10mm CS cutting gas consumption is about several hours/tank.

We recommend you use liquid gas, its cost will be much more lower then small tank. Most of our customer use it.

Thirdly. Running cost of fiber laser cutting machine-Quick wear parts
Main quick wear parts include nozzle and protective lens.
Then,1st year their consumption is about 20~30 pieces per year, but the cost will be decline later.
As their consumption have big relationship with workers operation.

Nozzle 10usd/pieceProtective lens 15usd/piece.
Then, nozzle and protective lens cost is about 500usd per year.

Lastly. Running cost of fiber laser cutting machine-Other parts.
Focus lens, ceramic rings and collimating mirror cost is not common quick wear part.
Then, you just need arrange 1 set for spare, their total cost is 350usd/set.

Therefore, the quotation is composed of the unit price of the line and the unit price of the hole.
Running cost of fiber laser cutting machine can calculation, for example, 3MM stainless steel with a length of 3 meters and 1.5 meters. If it is a package, you need to calculate the material cost (board purchase cost – scrap price) + one meter cutting unit price * cutting line length + punching cost * number of holes.

Contact:Karina Xiao

Wechat& whatsapp:008618206584205